CD1 electric hoist is a wire rope electric hoist, is a kind of light and small lifting equipment. It has the characteristics of small size, light weight, simple operation, convenient use and easy maintenance, is used in industrial and mining enterprises, storage docks and other places. CD1 electric hoist can be installed separately on the I-beam, or  electric or manual single beam crane, double beam overhead crane, jib crane, gantry crane and other cranes. The lifting weight is generally 0.1 to 80 tons, and the lifting height is 3 to 30 meters. How to safely use the CD1 electric hoist?
 
1. The electric hoist installed after the new installation or after the dismantling inspection should first be tested lifting several times.
 
2. Before normal use, the CD1 electric hoist should be carried out with a rated load of 125% rated load, lifted from the ground by about 100 mm, and a static load test for 10 minutes to check whether it is normal.
 
3. The dynamic load test is based on the rated load weight, repeated lifting and left and right movement test. After the test, check the mechanical transmission part, whether the electrical part and the connecting part are normal and reliable.
 
4. It is not allowed to press two flashlight button that moves the electric hoist in the opposite direction.
 
5. After the work is completed, the main power supply must be cut off.
 